Date: Fri 24-Jul-1998
Date: Fri 24-Jul-1998
Publication: Bee
Author: STEVEB
Quick Words:
BTI-Keith-Crumb-library-Booth
Full Text:
Library Contractor Still Pressing For Payments From The Town
BY STEVE BIGHAM
Keith Crumb, the contractor who began work on the $4.1 million Cyrenius Booth
Library project and was later fired due to a lack of progress, has let the
town know they haven't heard the last from him.
The builder claims he is still owed $300,000 that was never paid for work that
his company, Building Technologies, Inc (BTI) of Prospect, completed on the
library. Mr Crumb hopes he and the town can come up with some sort of a
settlement in the coming weeks. If not, the issue will most likely end up in
court.
"We'll be talking to the town. Whether we go ahead with a lawsuit will all
depend on how they react," he said Monday.
There have not been any lawsuits filed against the town by BTI to date. The
company is being represented by Ed Marcus of New Haven.
Lawsuits, if they ever get filed, may actually seek more than just payment for
services rendered. According to Mr Crumb, it may also seek damages for alleged
wrongful termination of contract and inflammatory remarks made by town
officials.
"There was some defamation. Some things were said," Mr Crumb noted.
Mr Crumb and BTI were fired last November after a unanimous vote by the Board
of Selectmen led at that time by Bob Cascella. Mr Crumb vowed at the time he
would eventually even the score in court.
"There will be several lawsuits filed," he said just moments after Mr
Cascella, Jim Mooney and Gary Fetzer voted him out.
The library project was five months overdue when the town finally decided to
fire BTI last year. Mr Crumb said much of the delay was due to the surprise
discovery of asbestos and lead in the walls of the existing building. It was a
situation Mr Crumb did not anticipate and had no control over. Cleanup efforts
stalled progress on the renovation work. BTI ended up being fined by US
Occupational Safety and Health Administration (OSHA) for continuing to work in
the health-risk areas.
For nearly three months last fall, the project remained at 95 percent complete
as BTI reportedly failed to get its sub-contractors on site. Mr Crumb claimed
most of them refused to show up because the town was not paying them.
Mr Crumb posted a performance bond when he began the project and First
Selectman Herb Rosenthal said the bonding company has since been writing
checks to the sub-contractors.
As for Mr Crumb, the first selectman said he hopes the town can work things
out without going to court.
"I don't know what's going to happen. We are going to try to settle the whole
thing up," Mr Rosenthal noted.
These days, Mr Crumb says he is still busy, but he is staying away from large
municipal projects, especially like the one in Newtown.
"I had so many different people to answer to," he said. "There was the first
selectman, the building committee, the library board. I needed a break from
that fiasco in Newtown."