Date: Fri 04-Jun-1999
Date: Fri 04-Jun-1999
Publication: Bee
Author: ANDYG
Quick Words:
Hawleyville-United-water-line
Full Text:
Pipeline Extension Expected To Set Stage For Hawleyville Development
(with photo & graphic)
BY ANDREW GOROSKO
In a move heralding the anticipated higher-density development of Hawleyville,
United Water plans to begin construction this summer on a 10,000-foot-long
water main to extend its public water supply service area from central Newtown
to Hawleyville.
Design plans for the project have been submitted to the Conservation
Commission for review. United Water is seeking commission approval to lay the
water pipeline beneath seven brooks, said Conservation Official C. Stephen
Driver. Mr Driver said he doesn't foresee problems with the project gaining
commission approval.
The water system expansion would extend the edge of the water service area
from the intersection of Middleton Road and Blackman Road westward generally
along Mt Pleasant Road to 166 Mt Pleasant Road, the 60-acre site of the
Homesteads at Newtown, a planned 298-unit housing complex for the elderly.
The extension of the public water line into Hawleyville, plus the planned
extension of sanitary sewers from Bethel into Hawleyville will set the stage
for higher density development of that largely undeveloped section of town.
United Water is extending the water system at the request of the Homesteads,
which will pay for the expanded water system, said Kevin Moran, United Water
manager.
"It opens the (development) possibilities for Hawleyville," Mr Moran said.
As a condition of approving the Homesteads last September, the Planning and
Zoning Commission (P&Z) required that the complex be served by a public water
supply and public sanitary sewers. Milone and MacBroom, Inc, the engineering
firm for the Homesteads, designed the water system extension.
In April, Avalon Bay Communities, a major apartment developer, submitted plans
to the town for Avalon at Newtown, a 304-unit multi-story apartment complex
proposed for a 40-acre parcel directly west of the Homesteads site. If Avalon
gains approval for its project, that complex would be served by yet another
extension of the United Water system.
The two complexes -- one approved and one proposed -- represent the two
largest private residential development projects ever planned locally. Such
complexes would not be possible without access to sewer lines and water lines,
Mr Driver said.
Mr Moran said United Water has been discussing a water line extension with Dr
Morton Silverstein of the Homesteads for at least two years. Mr Moran said he
only recently learned of the adjacent Avalon proposal.
Hydraulics
Due to the hydraulics involved in the water system extension, United Water
will install equipment to reduce water pressure in the line extending to
Hawleyville, Mr Moran said. Water is stored and released from a holding tank
at the end of Reservoir Road, atop Mt Pleasant. No water pumping stations will
be needed for the Hawleyville extension, Mr Moran said.
"We still continue to have quite a good reserve capacity," he said. United
Water has the ability to draw 1.5 million gallons of water per day from its
Pootatuck Aquifer wellhead across South Main Street from Sand Hill Plaza. It
currently distributes about 400,000 gallons per day to its approximately 1,000
customers. Mr Moran estimated that new demand for water by the Homesteads and
potentially by Avalon would be a total of less than 100,000 gallons per day.
In the past, United Water tested the groundwater reserves in Hawleyville, but
found there was insufficient water available for a public water supply, Mr
Moran said.
United Water's target price for the water line extension is $800,000, Mr Moran
said. The company was awaiting competitive bids on the project.
United Water plans to install a 12-inch-diameter plastic water pipe in the
shoulders of state and town roads in the water system extension. Shoulder
installation is done to minimize costs, limit traffic disruptions and speed
work. The company investigated the alternative of installing the pipeline
generally beneath the roadway, but that wasn't chosen because the state would
have required the entire pavement of Mt Pleasant Road to be replaced,
according to United water's application to the Conservation Commission. Such a
construction project would be very costly, disruptive to traffic flow and
would prolong construction work, according to United Water.
United Water avoids installing such water main extensions beneath pavement
wherever possible, Mr Moran said, noting that a majority of the pipeline to be
installed will not be beneath pavement.
The proposed pipeline would extend westward following the south side of
Blackman Road, the south side of Mt Pleasant Road, the north side of Tory
Lane, and again the south side of Mt Pleasant Road to the Homesteads site.
United Water chose the physically simplest route for a water main extension,
Mr Moran said.
In such a project, typically between 150 to 200 feet of water main is
installed daily, depending on ground conditions, he said.
According to Mr Moran, in the future, water service could be extended to
properties lying along that route by "wet tapping" the water main. Typically
the owners of good water wells don't quickly connect to new water mains, he
said.
About 1,000 feet of the 10,000-foot pipeline would be installed in areas
regulated by the Conservation Commission.