Date: Fri 03-Jul-1998
Date: Fri 03-Jul-1998
Publication: Bee
Author: ANDYG
Quick Words:
DOT-Route-25-widening
Full Text:
DOT Recommends Route 25 Widening Project
(with cuta
BY ANDREW GOROSKO
The state Department of Transportation (DOT) is recommending that Route 25 be
widened between Mile Hill Road in Newtown and Route 111 in Trumbull to improve
traffic flow on the heavily-traveled thoroughfare.
The widening recommendation is part of a draft environmental assessment of
proposed Route 25 road improvements prepared by DOT with the Federal Highway
Administration (FHWA).
The DOT plans to conduct public hearings in late September on its proposal to
widen Route 25, said Keith Hall, DOT's manager on the Route 25 project.
Mr Hall said no construction starting date has been set for the proposed
widening of the state road.
After public hearings on the proposal are conducted this fall, DOT planners
will be able to better gauge a schedule for such a project, he said.
The widening work proposed by DOT would cost approximately $82.5 million in
construction costs in current dollar value, Mr Hall said. Acquiring
rights-of-way for road widening would add to that price.
A more extensive road widening project which was considered but turned down by
the DOT would have cost $144.3 million.
Route 25 is a primary link between Interstate-95 to the south and
Interstate-84 to the north in southwestern Connecticut. Improvements are
needed to Route 25 due to current inadequate road geometry, inconsistent
speeds, inadequate access control, expected growth in the corridor leading to
higher traffic volumes, and safety problems, according to DOT.
The proposal to widen the road or build a new version of it has been discussed
for decades.
In reviewing what should be done to improve traffic flow on Route 25, DOT
considered: doing nothing; fully widening the two-lane Route 25 into a
four-lane road with the construction of 15-foot-wide median strip, plus wide
outside road shoulders; or doing a limited widening of the road, which is
DOT's preferred alternative.
Under the preferred alternative Route 25 would be widened on its existing
alignment to two through-lanes in each direction between Route 11 in Trumbull
and Mile Hill Road in Newtown. The road would have four 12-foot-wide travel
lanes and two two-foot wide outside road shoulders. The road's right-of-way
would be 75 feet wide. Auxiliary turning lanes would be added at major
intersections as judged feasible to do so.
The DOT states that, at a minimum, exclusive left-turn lanes would be added on
the Route 25 approaches to four existing intersections with traffic signals.
These are: Route 111 in Trumbull; Purdy Hill Road/Judd Road in Monroe; Route
59 in Monroe; and Bradford Drive in Monroe. "The intersection of Route 25 and
Mile Hill Road in Newtown... will also require additional turning lanes beyond
those provided as part of the widening of mainline Route 25 itself," according
to the DOT.
The DOT opts to terminate a widened Route 25 at Mile Hill Road because Mile
Hill Road is being rebuilt as the Fairfield Hills bypass road and will provide
good access to Interstate-84 via Exit 11.
In the 1980s, before such a bypass road was planned, DOT had been planning a
widening of Route 25 that would have terminated at the Main Street flagpole,
which was then the most direct means of getting to I-84 via Exit 10.
To reduce the effect on structures and resources adjacent to the widened road,
the DOT proposes using minimum design standards in the road widening. With
such planning used, the improved road would eliminate or reduce the severity
of conflicts between the users of Route 25 and its intersecting roads,
according to the DOT.
If a "limited" road widening occurs, the DOT estimates the total number of
structures in Newtown which might be acquired by the state are four
residential properties, and three commercial/industrial properties.
"The estimate does not include properties that could be affected by severe
parking or lot area impacts. Efforts will continue to be made to further
minimize potential impacts related to the limited widening alternative during
preliminary design through further shifts in alignment," according to the DOT
report.
"This is all in the planning stages. When it's in design (stages), we will do
all we can" to limit the state's acquisition of properties for road widening,
Mr Hall explained.
The DOT states the limited widening alternative would have substantially less
impact on properties adjacent to Route 25 than would the full widening
alternative.
Copies are of the extensive DOT report on the project are available for local
review at the town clerk's office at Edmond Town Hall, 45 Main Street; the
Booth Library, reference department, 25 Main Street; and the Housatonic Valley
Council of Elected Officials, Old Town Hall, Route 25, Brookfield Center.