Date: Fri 11-Sep-1998
Date: Fri 11-Sep-1998
Publication: Bee
Author: CURT
Quick Words:
NU-ruling-rate-energy
Full Text:
Judge Rules That Rate Payers Shouldn't Pay For Nuclear Plant Mismanagement
By Brigitte Greenberg
Associated Press
NEW HAVEN -- Northeast Utilities cannot foist the entire $427 million bill to
decommission the old Connecticut Yankee plant onto rate payers because the
company mismanaged the facility, a federal judge has ruled in a preliminary
decision.
Attorney General Richard Blumenthal last week hailed the recommendation from
Federal Energy Regulatory Commission Administrative Law Judge William J. Cowan
as a "major victory" that could save consumers as much as $200 million.
The 117-page decision was August 31 by the US Department of Energy. Cowan said
his conclusion that the company's imprudent actions were to blame for the high
cost of mothballing the plant was "inescapable."
NU owns 49 percent of the plant, which it operates. The judge found the
company's estimate of decommissioning costs was error-ridden, and failed to
support its request for $82 million to return the plant's Haddam Neck site to
its original condition.
The judge's recommendations will be forwarded to the full, five-member
commission that makes the final decision. Before that, both sides have about
two months to file objections to the judge's findings. Either side also can
appeal the decision of the full commission, which could come at any time.
Connecticut Yankee spokeswoman Kelley Smith said plant executives were
considering whether to argue against the judge's ruling.
"Right now, this is just the first step in a very long process. We're in the
process of reviewing the decision in order to fully understand the
administrative law judge's reasoning," Smith said. "We haven't made any
decisions."
Despite the ruling, decommissioning will continue, Smith said.
The plant closed in 1996, when the company concluded it would be cheaper to
buy power elsewhere than to continue running the aging plant. State officials
said it closed early after deteriorating because of inept management. The
plant closed 11 years before its license was to expire.
A state-hired consultant found that radiation had leaked from the reactor onto
the grounds, and some contamination was spread through the removal of fill to
land once used as the site for a day care center. State officials said,
however, that the radiation levels did not pose a public health threat.
Cowan accepted the state's arguments, saying the "evidence paints a pretty
clear picture of drains carrying radioactive contaminants that were unmarked
and uncontrolled, sloppy work habits around radiologically contaminated
materials that went uncorrected, careless handling of radwaste outdoors, and
uncontrolled or poorly monitored movement of contaminated materials on- and
off-site."
The plant also should not be able to rate payers $90 million for spent fuel
storage costs because those charges are the responsibility of the Energy
Department, the judge said.
The decision rejects Connecticut Yankee's request for a rate increase and sets
temporary rates at a previously approved level, close to $350 million.
If the recommendation is adopted, the company will not be able to collect $78
million for decommissioning costs and will not get an additional $70 million
in returns on the plant owners' investment. Also, the decision could exclude
an additional $50 million that the plant wanted to charge its customers.