  • Ambulance Garage Work Continues Despite The Cold

    At 18 degrees and sunny, carpenters with Nosal Builders worked steadily Wednesday to get the roof structure in place. Clerk of the Works Brian Feeney said the progress on the Newtown Volunteer Ambulance Corp’s new ambulance garage is “going really well.” So far, the roughly $4.5 million project that broke ground in mid-2013, is on schedule, he said.

    Roofing trusses were going into place this week and that phase of the roof should be completed in a few weeks, Mr Feeney said.